The purpose of the project: To apply the latest technological advancements to establish the production of 3,000 tons of green hydrogen annually from eco-friendly raw materials that can replace natural gas. This project ensures both high profitability and a solid foundation for the widespread adoption of green technologies in the national chemical industry, particularly in the production of mineral fertilizers.
• In addition, it contributes to the energy independence of enterprises and aligns industrial processes with environmental objectives.
• The project cost amounts to USD 88 million.
Key expected outcomes of the project:
• Project capacity: 3,000 tons per year
• Product: Green hydrogen
• Investor: “ACWA Power” (Saudi Arabia)
• Jobs to be created: 35 positions
• Contractor: “Power China Huadong Engineering” (China)
• Project implementation period: 2023 – 2025
• Generation capacity: 52 MW (wind energy)